top of page

Building Statistics I

Building Name:

 

Building Location:

 

Occupant Name:

 

Size:

 

Number of Stories:

 

Construction Date:

 

Construction Cost:

 

Project Delivery Method:

 

 

 

Hotel Building Ohio Valley Region

 

Ohio Valley Region

 

Major Hotel Service

 

79,000 SF

 

10 Stories Above Grade

 

June 2014- August 2015

 

$13.3 Million

 

Design Buid Build

 

Project Team

Owner:

 

Construction Manager:

 

Architect:

 

MEP Engineer:

 

Structural Engineer:

 

Civil Engineer:

 

Hotel Owner

 

Massaro Corporation

 

JMAC Architects

 

Allen & Shariff Engineering

 

Atlantic Engineering Services

 

Lennon, Smith, and Souleret Engineering Inc.

 

 

Architecture

The hotel located in a city in the Ohio Valley.  Surrounded by other hotel chains that supply to the cities many amenities.  It is a ten story building, with a first floor lobby, seating area, and workout center.  Floors 2-10 consist of multiple ranges of rooms that include queen, king, and ADA accessible options.  The general architecture of the building is to replicate the building exteriors of surrounding buildings in the area. 

Code

International Building Code 2009

 

International Fire Code 2009

 

International Mechanical Code 2009

 

International Energy Conservation Code 2009

 

International Electric Code 2009

 

National Fire Protection Association 13

 

 

Zoning

Type 1B per Ohio Valley City (Location Withheld) building zoning

 

High Rise building Classification

Historical Requirements

No Historical Requirements

Building Enclosure

The building façade is consistent on each elevation of the building.  It includes a cast stone veneer on the first three floors and brick façade from floors four thru ten.  On the front elevation facing the main traffic street there is a curtain wall façade incorporated into the lobby.  The basic wall structure is shown in Figure 1. 

Building Facades:
Roof:

The roof system shown below is placed below a parapet that varies in height around the building exterior.  The material properties of the roof system include a membrane system, with tapered insulation below on top of a precast concrete slab, with an interior ceiling finish leading into the hotel rooms.  Shown via Figure 2.

Figure 1: Building Facade Detail

Figure 2: Roof System Detail

Building Statistics II

Construction

The site has multiple constriants in laydown area and safety.  To the north of the site a raised highway is a concern for the crane crew when lifting materials. Another logistical problem is the lack of laydown area on site.  Therefore three lanes of the street to the west of the site are used for laydown and space for a mobile crane to be used.  

The electrical utility power that is provided to the hotel is via one transformer, located in the basement electrical room.  The transformer feeds one main switchboard that is 3000A, 208Y/120V, 3 phase, and 4 wires. The power is distributed to 41 individual panel boards.  The standby system is a 3000W diesel engine generator with 660 gallon fuel tank.

Electrical

Each hotel room has a master control as you enter the room that feeds the bedroom and bathroom.  Task lighting surrounds the room on the desks as well as next to the bed.  Lighting in halways and the lobby are tubular flourescent. 

Lighting

The building’s major mechanical system supplies the lobby and hallways in the building is the roof top unit (RTU).  The boilers and pumps are located in the mechanical room in the basement.  All guest rooms are conditioned by Packaged Terminal Air Conditioners (PTAC) and are controlled by the individual user.  The pool has a dehumidification unit placed on ground level behind the building on the East side.  The sprinkler system is hidden in the ceiling panel and serves each guest room. 

Mechanical

The building’s structural system consists of ten stories of precast hollow core floor slabs that are capable of holding 20 psf dead load, with 80 psf for movable material load, and live load per specific design criteria.  These hollow core floor slabs will be lifted into place via crane.  These floor slabs will be set on a concrete masonry unit bearing structure.  There is a one floor slab on grade basement with electrical and mechanical equipment. 

Structural

The jocky pump is located in the basement that feeds sprinklers on all floors.  A floor control is located in the stairwell in the center of the building. the system runs throught the center of the hallways and there are wall mounted units in each hotel room.   

Fire Protection

Each hotel room is provided with a phone jack, calbe television possibilities, as well as internet connection either wired or wireless.  All electrical systems are fed from an individual electrical closet on each floor.  

Telecommunications

Transportation

There are two stair wells located in the building.  One to the north part of the building and one at the center next to the elevator lobby.  As well as the two stairwells, there are two elevators that reach every floor within the hotel.  

bottom of page